Project Case Studies

See what our clients needed and how we moved the work forward.

Each case brings together the brief, supplier work, site records, and the latest project update.

Project updates

Where each project stands today.

See the original brief, the work already handled, and what comes next.

Browse evidence by type
DestinationProject scopeCompleted workCurrent statusUpdated
Shenzhen, ChinaTwo days of original field evidence, recorded discussion, model schedules and an order-readiness report2 days of fieldwork · 31m53s recorded discussion · 2 exact model schedulesField-review milestone completed · evidence updated August 15, 20262026-08-15
Gold Coast, AustraliaSite measurement, multi-category sourcing, and design-change coordination21 site photos · 3 zone walkthrough videos · 1 source structural DWGOngoing · evidence updated July 29, 20262026-07-29
West Africa (anonymized)461 BOQ pages organized into 28 sourcing packages461 BOQ pages · 28 sourcing packages · 1,420 product referencesPlanning milestone completed · evidence updated July 27, 20262026-07-27
Oregon, United StatesDrawing-led windows, finishes, packing, and logistics coordinationApprox. 4,200 SF · 55 buying tasks · Plans, elevations, and rendersOngoing · records consolidated July 26, 20262026-07-26

Living project case studies

What the client needed, what we handled, and where the project is now.

Follow each project from the original brief through the work completed and the latest update on August 15, 2026.

Latest verified
Public project records
4
Countries and regions
4
Clear status
Ongoing + milestones
Field-review milestone completed · Shenzhen, China

IWF Shenzhen & INSIGHT Equipment Review

Two days of original field evidence, recorded discussion, model schedules and an order-readiness report

Buyer problem

The buyer had already selected INSIGHT and needed FoshanBuild to test that choice against the market, recover the supplier's product and factory claims from the recorded discussion, compare two exact packages and define what must be locked in writing before deposit.

Latest update

The IWF market scan, focused INSIGHT validation, 31m53s recording review, two model schedules and client report are complete; written model specifications, export packing, warranty, final layout and PI are the next gate.

Record
2 days of fieldwork
Record
31m53s recorded discussion
Record
2 exact model schedules
What FoshanBuild did
  • Indexed 55 original field files from IWF Shenzhen and the focused INSIGHT/commercial-application review.
  • Converted 31m53s of discussion into evidence-labelled product, customization, manufacturing, export, commercial and service findings.
  • Normalized the 11-item and 14-item packages at model level and prepared a bilingual report, supplier-route matrix, quotation review and P0/P1 order-readiness checklist.
Current result / stage

INSIGHT remains the priority route and the 14-item structure is the preferred planning baseline. Model specifications, black-on-black production details, export packing, warranty/service responsibility, final layout and PI remain pending.

Read the full field-review record
Ongoing · Gold Coast, Australia

Australian Gold Coast Residence

Site measurement, multi-category sourcing, and design-change coordination

Buyer problem

A private residence needed reliable site records, coordinated Foshan selections, and controlled design changes across custom joinery, appliances, furniture, lighting, and related materials.

Latest update

The site record is complete and the active kitchen brief now reflects the island cooking layout, revised oven direction, and outstanding Australian compliance evidence.

Record
21 site photos
Record
3 zone walkthrough videos
Record
1 source structural DWG
What FoshanBuild did
  • Prepared a site-measurement brief covering access, room scope, door and window openings, ceiling heights, beams, columns, kitchen and bathroom conditions, service points, and photo indexing.
  • Coordinated the local site team and organized the returned field record for the client, designers, and China-side suppliers.
  • Supported the Foshan selection program and organized working references for cabinetry, appliances, lighting, furniture, outdoor items, drawings, BOQ, and supplier comparison.
  • Recorded the latest kitchen revision: the wall cooktop and hood were removed, the cooking system moved to the island, and the oven direction was reselected.
Current result / stage

The project is active. Revised drawings, exact appliance specifications, supplier technical information, and Australian compliance evidence remain under coordination.

Read the full field-review record
Planning milestone completed · West Africa (anonymized)

Coastal Resort Procurement Planning

461 BOQ pages organized into 28 sourcing packages

Buyer problem

A coastal resort brief contained thousands of procurement references that had to be separated into China-supply, technical-clarification, and local-contractor scopes before reliable supplier RFQs could begin.

Latest update

We have reviewed all 461 BOQ pages and divided the work into 28 sourcing packages. The client is now choosing which packages to quote first.

Record
461 BOQ pages
Record
28 sourcing packages
Record
1,420 product references
What FoshanBuild did
  • Reviewed the full BOQ and classified six priority RFQ packages, 15 provisional or clarification-led packages, and seven local-contractor-led packages.
  • Translated lagoon-side humidity, salt-spray, UV, and corrosion exposure into material, coating, fastener, IP/IK, warranty, maintenance, and packing evidence requirements.
  • Prepared the first planning budget, with logistics, taxes, installation, commissioning, and local engineering listed separately for later confirmation.
Current result / stage

The scope-review and budget-planning milestone is complete. Client priority decisions and supplier-backed technical quotations remain pending.

Ongoing · Oregon, United States

Oregon Custom Residence

Drawing-led windows, finishes, packing, and logistics coordination

Buyer problem

A custom residence needed design intent mapped into comparable product workstreams before windows, doors, flooring, stone, packing, and logistics decisions could be controlled.

Latest update

The plans, elevations, renderings, and product requirements are now sorted by room and category, ready for supplier comparison and quotation work.

Record
Approx. 4,200 SF
Record
55 buying tasks
Record
Plans, elevations, and renders
What FoshanBuild did
  • Reviewed anonymized plans, elevations, renderings, and schedules for room-by-room product coordination.
  • Grouped window and door elevations, garage-door information, hardware systems, timber flooring, stone, and exterior-finish directions.
  • Organized specification, quotation, packing, and logistics questions against the available project documents.
Current result / stage

Product coordination remains active. Final quantities, specifications, ordering, and installation depend on confirmed project documents and local professional approvals.

Detailed case articles

See how specific project problems were handled through field images and working records.

Each article starts with a real project problem and shows how we worked through it.

Browse all articles
Anonymized indoor photo of a tall bookcase carcass assembled during residential installation. Australian project case

Australian Home Cabinetry: From Delivery to On-Site Installation

This project follows bookcase, walk-in wardrobe, and kitchen cabinetry after arrival at an Australian home, including the installation progress and the final steps still to be completed.

Project case · Updated 2026-08-08 View case details
Anonymized window units staged on a factory rack for visual quality review. Window factory check

Window Factory Checks: What Photos Show and What Documents Must Confirm

We checked window units, tracks, hardware, and dimensions at the factory, while treating NFRC, AS 2047, and other technical documents as a separate review.

Project case · Updated 2026-08-08 View case details
Tape measure placed across a dark tabletop in a separate anonymized product QC record. Project record guide

How We Organize Project Photos: Installation, QC, and Factory Records

These images come from separate projects. We show installed work, installation in progress, product checks, and factory assembly separately so they are not mistaken for one order.

Project case · Updated 2026-08-08 View case details
Original wide field photograph of the IWF Shenzhen 2026 exhibition hall with commercial fitness-equipment booths visible below. Project case

Two Days in Shenzhen: IWF Comparison, INSIGHT Validation, and an Order-Ready Equipment Review

A material-led record of how FoshanBuild reconstructed the buyer brief, scanned IWF Shenzhen, validated the already-selected INSIGHT route, reviewed original photos and 31m53s of recorded discussion, normalized two equipment packages, and defined the written gate before order.

Project case · Updated 2026-08-17 View case details

Continue researching

Keep real cases, planning models, and evidence records separate.

Evidence Library

Browse completed work across BOQ, site capture, supplier comparison, and QC.

Open
Budget Models

Build an early budget starting point from area, category mix, and quality tier.

Open
Global service map

Explore regions where FoshanBuild is ready to start supporting buyers.

Open
Buyer Working Templates

Download the sourcing brief, pre-shipment inspection report sample, and packing and loading checklist.

Open
Services and deliverables

See the procurement, QC, packing, handoff, and responsibility boundaries.

Open

Send your furniture, building-materials, or project list on WhatsApp.

We will tell you what is missing and what the next buying step should be.

Send Your List on WhatsApp

Contact Vincent directly

For both new and existing projects, you can now contact Vincent directly on WhatsApp.

Message Vincent on WhatsApp

Unable to open WhatsApp? info@foshanbuild.com

WhatsApp